Durban Gateway Terminal faces licence threat as operator blames old equipment for 20-day ship queues

Durban Gateway Terminal faces licence threat as operator blames old equipment for 20-day ship queues

Durban Gateway Terminal (DGT), the container terminal that handles almost half of South Africa’s containerised freight, is under pressure from government and industry after ship waiting times stretched to as long as 20 days. On Thursday 19 November 2026 the operator admitted “continued service short comings” and blamed the poor and unsafe condition of its equipment, according to a Bloomberg report published on Moneyweb. Transnet, meanwhile, has announced a package of emergency measures. This article sets out what each party has said and what is still unclear.

What the terminal operator said

The Bloomberg report, by Matthew Hill, says the terminal has been run since the start of 2026 by Manila-based International Container Terminal Services Inc (ICTSI), brought in as a private investor because the facility needed heavy investment. The report says the new public-private model has yet to produce results, and that the terminal has long ranked among the world’s worst ports for efficiency.

In a statement responding to the government’s threat to revoke its port licence, DGT acknowledged the impact of the delays on clients and partners. It said the core issue was “the poor and unsafe condition of equipment at the facility, owing to years of under-investment”. That is a pointed claim, because it places much of the responsibility on the state-owned infrastructure the operator inherited.

A week earlier the tone was different. According to a separate Moneyweb report, DGT said in a statement on the previous Friday that conditions had stabilised. Chief executive Javier Lancha was quoted as saying the operational recovery programme “has restored terminal fluidity and positioned the terminal to absorb seasonal pressure”. The same report says DGT has committed more than R2 billion over three years to upgrade equipment and infrastructure at Pier 2.

The licence threat

The Bloomberg report says government has threatened to revoke DGT’s port licence if waiting times do not improve, but gives no deadline or licence terms. The Moneyweb report is more specific. It says Transport Minister Barbara Creecy told SAfm that the Transnet National Ports Authority (TNPA) has given ICTSI three months to improve performance or risk losing its licence. We have not seen the TNPA’s own wording, so that deadline rests on the minister’s reported remarks.

Creecy also told Radio 702, as reported by Bloomberg, that government is diverting ships to other terminals and prioritising vessels carrying automotive parts and medicines. She acknowledged that the port’s equipment needs investment, but criticised DGT for introducing a new operating system just before the peak festive season. In an EWN report on her interview with The Money Show, she linked the problems partly to the new Navis N4 system, which is delaying trucks, and said ICTSI “needs help” and that Transnet is providing it.

Transnet’s emergency measures

Transnet announced its interventions on Wednesday 18 November. In the press release as republished by Infrastructure News, the state logistics group said it would:

  • Make Berth 102 available for geared vessels that discharge directly, through TNPA.
  • Divert vessels to the Ngqura Container Terminal, with containers then moved to Berth 102 and the Point Terminal on smaller geared vessels.
  • Bring refurbished ship-to-shore cranes back from Pier 1, with the final crane due to be commissioned on Friday 20 November and handed to operations the next day, bringing all six cranes into service.
  • Provide trains through Transnet Freight Rail to move import containers bound for Gauteng.
  • Prioritise essential cargo, such as pharmaceuticals and auto parts, for evacuation before berthing.

The release gives no backlog size, vessel counts or clearance timeline. Moneyweb adds that Berth 102 is a single berth with annual capacity of 700,000 TEUs (twenty-foot equivalent units), against two million TEUs a year at DGT’s six operational berths on Pier 2. Diverted volumes therefore cannot replace the terminal. EWN reports that 18 vessels carrying medicine containers need unloading, and that Transnet is working with shipping lines to unload them immediately.

The business cost

Bloomberg says the delays have caused medical supply shortages and hurt car exports. Neale Hill, president of Ford’s South African unit, said the delays and uncertainty raise logistics costs and undermine the competitiveness of the automotive industry, and urged the parties to resolve the uncertainty urgently and clarify the way forward.

According to Moneyweb, Metair Investments, which supplies Ford, Toyota and Isuzu, has said it might invoke force majeure on supply contracts. The same report says truck operators describe delays of up to 22 hours at the terminal. These are claims by the companies and operators concerned, and we have not independently verified them.

What remains unresolved

Several questions are open. The operator blames old equipment, while the minister points to a poorly timed operating system change and to a shortage of straddle carriers, the machines that stack containers. Creecy told EWN that ICTSI said it was “scouring the world” for extra straddles. Neither the Bloomberg report nor the Transnet release says when the terminal will return to normal working, and the Bloomberg report includes no response from Transnet on the licence.

For importers and exporters, the practical advice is to expect continued delays through the festive peak, and to check with shipping lines about diversion to Ngqura. For more on the terminal’s labour and equipment pressures, see our earlier reports on former Transnet workers recalled to cover the backlog and on Transnet’s recovery plan. The headline report is Bloomberg’s piece on Moneyweb, which is news reporting, not opinion.