The National Energy Regulator of South Africa (NERSA) has opened public comment on amended Cost Recovery Rules for Independent Transmission Providers, and written submissions must reach it by 2 December 2026, according to its official notice. The Energy Regulator approved publication of the consultation paper and the draft amended Rules on 29 October 2026, and a virtual public hearing follows on 7 December 2026 from 14:00 to 17:00.
What this means for your business
The Rules govern how the buyer of transmission capacity from private providers recovers what it pays, not how the private providers themselves are regulated. NERSA’s consultation paper says that where NERSA finds the costs efficient and cost-effective, the costs of increasing transmission capacity will be passed on to customers through the tariffing process. That makes the Rules relevant to anyone who buys grid electricity, whether a factory, cold chain, mine, farm or property portfolio. The paper does not estimate any effect on tariffs. NERSA’s notice asks stakeholders and members of the public for comment, so a business does not need to be an energy company to take part.
What NERSA has actually published
NERSA says it is amending the Rules “to address key regulatory issues”. The consultation paper, published on 30 October 2026, explains them. The Rules were approved by the Energy Regulator on 2 December 2025, and NERSA says stakeholder feedback raised concerns that some provisions could hurt the bankability and funding of projects. The proposed amendments, it says, aim to reduce regulatory uncertainty, strengthen cost recovery certainty and support project bankability, and are limited to specific aspects and not a full review. The paper lists six areas:
- The title. NERSA proposes renaming the Rules “Cost Recovery Rules for Transmission Capacity Purchases”, because they do not directly regulate the private providers but give the buyer certainty about recovering eligible costs.
- The definition of termination costs, which NERSA says was read differently by some stakeholders and may have excluded some legitimate costs.
- The principles of cost recovery, with the principles separated from the criteria for assessing cost-effectiveness.
- Authorisation, where “a reasonable margin or return” would become “a risk-adjusted return”, to align with the amended Electricity Regulation Act.
- Recoverable costs, listed as transmission capacity payments including indexation, administration costs, termination costs and other costs such as hedging and insurance. The draft excludes the part of any termination cost that reflects fraud, tender manipulation or bidder collusion.
- No double counting of costs, with costs already recovered to be clawed back and reconciled through tariff adjustments.
The paper asks five questions, covering the title, termination costs, the principles of cost recovery, authorisation and recoverable costs. The consultation paper and draft amended Rules are on NERSA’s consultation notices page.
The key dates and contacts, all taken from the notice:
- Written comments go by email to crr4itps@nersa.org.za, and the closing date is 2 December 2026. The paper says submissions after the deadline will not be considered.
- The public hearing is on 7 December 2026, on Microsoft Teams, from 14:00 to 17:00.
- Anyone who wants to attend or present at the hearing must ask by 16:30 on 2 December 2026, via publichearings@nersa.org.za or 012 401 4660.
- NERSA says it keeps the right not to hold the hearing if no one asks to present by the closing date.
- Queries go to Mondli Shozi at NERSA on 012 401 4600.
That last point about the hearing is easy to miss. A hearing that attracts no requests may simply not take place, so silence from businesses can mean the discussion happens without them.
Why the rules exist
According to the consultation paper, grid constraints, delays in the Transmission Development Plan and limited resources led government to introduce the Independent Transmission Projects Programme, which uses competitive procurement to attract private investment in transmission. NERSA developed the Rules to give the buyer a clear, predictable and transparent framework for recovering efficiently and prudently incurred costs. NERSA says it approved the Rules on 2 December 2025 and shared them with the Department of Electricity and Energy for the request for proposals consultation package, to test them against market expectations.
The Rules went through an earlier consultation. NERSA first published draft Cost Recovery Rules for independent transmission projects on 26 September 2025, with comments originally due on 27 October 2025. It later extended the deadline to 23:59 on 3 November 2025 after requests for more time, Green Building Africa reported. In that report NERSA called private involvement in transmission “a new development in South Africa” and said it wanted a balanced approach that protects consumers, licensees and investors.
The solar trade body SAPVIA, in a note to members in October 2025, said NERSA had drafted the rules so that consumers contribute to a reliable transmission grid while investors can recover efficient investment costs. The October 2026 notice, as SolarQuarter summarised it, repeats the dates above and the invitation to stakeholders.
Where this sits in the grid timeline
The Independent Transmission Projects programme itself has slipped. As we reported, the final request for proposals moved from the third quarter of 2026 to the second quarter of 2027, with a second draft package going to seven pre-qualified bidders before the end of 2026. Cost recovery rules are one of the things bidders and lenders need settled before they can price a line, so the December deadline is part of the same path.
Grid access is also the constraint on the private power that many businesses already buy. Delegates at Windaba 2026 heard that grid capacity is becoming a limit on private wind projects. And if you are weighing a supply deal now, the regulator has separately set a hearing on 7 December for an electricity trading licence for Engie and an import-export licence for the Energy Exchange of Southern Africa. The two hearings fall on the same day, at different times, so a business or industry body that wants to follow both should plan for it.
What to do or watch
- Download the consultation paper and the draft amended Rules from the NERSA website this week and read the questions NERSA asks.
- Ask your finance or energy lead what share of your electricity cost is network charges, and whether a change in how transmission costs are recovered could reach your tariff, then decide if that is worth a comment.
- If you belong to an industry body, find out whether it is preparing a consolidated submission, as SAPVIA did in 2025, and send it your numbers before its internal deadline, which will be earlier than 2 December.
- Email your written comments to crr4itps@nersa.org.za by 2 December 2026.
- If you want to speak at the hearing, register by 16:30 on 2 December, since NERSA may cancel the session if nobody does.
- Watch for the second draft of the transmission tender documents, due to bidders before the end of 2026.
What we could not confirm
- The full wording of the draft amended Rules. We read the consultation paper but not Annexure B in full.
- Whether the amendments would raise or lower the cost to electricity users. NERSA’s notice and paper say nothing on tariff levels.
- Whether NERSA will extend the 2 December deadline, as it did in 2025.
Correction, 11 November 2026: an earlier version of this article said the Rules decide how a private company that builds and runs high-voltage power lines is allowed to recover what it spends. NERSA’s consultation paper says the Rules govern how the buyer of transmission capacity recovers its costs and do not directly regulate the private providers. The earlier version also did not say that NERSA approved the Rules on 2 December 2025. It has been corrected.